가이드 연계 퀴즈 · 중간 레벨
AI 퀴즈로 프로젝트 현황 보고서 작성하는 방법
AI를 사용하여 증거 기반 프로젝트 업데이트 초안을 작성하는 동시에 예측과 실제를 분리하고 위험, 등급 및 결정을 설명합니다.
질문 1 의 8
What should a status report compare progress against?
모든 질문 미리보기8 질문
퀴즈를 풀면 정답과 설명이 나타납니다.
- What should a status report compare progress against?
- An approved plan or baseline and its reporting date
- A target invented by AI for the summary
- The original idea without later changes
- The previous report’s wording regardless of new evidence
- AI labels a milestone “completed” based only on its task name. What should the lead do?
- Accept the label because it is concise
- Verify completion against project evidence and correct the draft
- Change all remaining tasks to complete
- Use the report as proof the deliverable was accepted
- How should a report handle red-amber-green thresholds?
- Assume colors mean the same in every organization
- Choose colors based on which looks reassuring
- State and apply the project’s documented definitions
- Let the model create thresholds after seeing results
- What distinction should a status report preserve?
- Forecast dates are already achieved dates
- A risk and an issue are always identical
- Budget forecasts replace schedule evidence
- Actual results differ from estimates and forecasts
- Actual spending is below plan, but the forecast total exceeds budget. What is clearest?
- Report favorable actual spend and unfavorable forecast separately
- Call it green based only on current spending
- Hide the forecast until overspend occurs
- Replace the forecast with the current actual
- What does the GAO guide say about schedule-report detail?
- Every stakeholder needs the same full schedule export
- Frequency and detail can vary by stakeholder and project complexity
- Only final dates should be reported
- Every project needs a fixed monthly cadence
- Schedule and risk log disagree about a delivery date. What should the AI draft do?
- Choose the optimistic date
- Average the dates and call it a forecast
- Flag the conflict for the owner to reconcile
- Delete both sources
- Beyond progress, what should a status report help readers identify?
- A guaranteed completion date
- A reason to avoid discussing risks
- A color that replaces explanations
- Risks, issues and decisions or escalations needing attention